top of page

Construction Journal December 2003

Writer's picture: LishaLisha

We got the official call from Bob at Canyon National Bank that the loan is ready to fund. Mark and I let out a huge sigh of relief.

We had submitted the plans at the end of November and two weeks later they were returned for corrections. We were actually quite pleased that it was so quick. We had heard horror stories about how difficult the county was to work with and that they took absolutely forever. So far with us, they were great. The corrections were a couple for engineering and then a ton for codes. When we hired Audrey she was about to submit plans to Riverside County for another client. Unfortunately, the clients decided to put it on hold, so she had not worked with this county before. We sent the plans back to her and Tony for corrections.

16 views0 comments

Recent Posts

See All

Construction Journal November 2004

It has rained and rained and rained. I think someone forgot to tell the weather that we are a DRY desert. It started raining the last...

Construction Journal October 2004

October so far has been spent mostly wrapping the house’s exterior and interior. For the exterior, we used 1x2 fencing and the inside was...

Construction Journal September 2004

September was an eventful month for our family! Here is the cliff notes version: Back in February Mark got what we thought was a bite on...

Commentaires


Stay up to date with DesertStrawHouse

Thanks for submitting!

Address:

16300 Bennett Road

Sky Valley, CA 92241

SUMMER HOURS

APRIL: BY APPOINTMENT ONLY

MAY-SEPTEMBER: CLOSED

October-March Hours:

Monday: Closed

Tuesday: Closed

Wednesday: By Appointment

Thursday: 9:00-5:00

Friday: 9:00-5:00

Saturday: 9:00-5:00

Sunday: By Appointment

  • Facebook
  • Instagram

©2020-2023 by DesertStrawHouse

bottom of page